EV-80Notes

Blog

  1. N-18

    Borrow pit volume vs. on-site cut: two different numbers in a haul plan

    Cut volume and borrow quantity measure different things. Mixing them up throws off haul counts, truck scheduling, and the pay app line items.

    A cut bank of excavated earth beside pasture, with a grader visible in the distance on a rural grading job.
  2. N-17

    Field notes: the week erosion ate a week's worth of cut, and the GC called it theft

    A storm moved dirt nobody hauled, and the pay app numbers took the blame. What weekly surface capture shows when erosion eats a week's cut.

    A bulldozer sits atop an eroded dirt slope with a drainage culvert pipe, dark storm clouds overhead.
  3. N-16

    How to size a haul truck fleet from a weekly cut volume report

    A worked method for turning a weekly cut volume into a truck count: cycle time, bed capacity, swell, and where the errors creep in.

    A dump truck parked on a dirt haul road at a quarry, with dry hills and a cloudy sky in the background.
  4. N-15

    What is an import/export balance on an earthwork job?

    What an import/export balance means on an earthwork job, how it's calculated, and why it drives your haul plan and pay app numbers.

    Large mounds of excavated soil sit under an evening sky, with utility poles in the background.
  5. N-14

    Field notes: the stockpile that disappeared between two Tuesday flights

    A foreman's trucking sheet and a vanished stockpile didn't add up. Two weekly drone flights showed where the yards actually went.

    A large stockpile of loose soil at dusk, with utility poles and power lines in the background.
  6. N-13

    Separating topsoil strip volume from subgrade cut on a pay app

    How to split topsoil strip volume from subgrade cut on a pay application using separate surface comparisons instead of a percentage guess.

    A cut bank of excavated earth in a rural field, showing a thin topsoil layer above the exposed subgrade.
  7. N-12

    Attaching a drone volume report to your AIA pay application

    How to attach a drone-based cut/fill volume report as G703 backup, matched to your schedule of values line items.

    A motor grader stands ready on a freshly graded dirt construction site, with another piece of heavy equipment parked nearby.
  8. N-11

    What a digital surface model is, and why earthwork volume surveys need two of them

    A DSM captures ground elevation at one moment. A cut/fill volume comes from differencing two of them, before the cut and after.

    Stockpiled mounds of excavated soil along a gravel site road at dusk, with utility poles silhouetted against the sky.
  9. N-10

    Field notes: the week the load count didn't match the pad

    A field-notes piece on the week a dirt sub's load count drifted from reality, and why nobody flagged the gap until the pay app was already due.

    A loaded dump truck hauling material down a dusty jobsite road in low sunlight.
  10. N-09

    How to document a differing site condition with drone survey volumes

    Building a differing site condition claim that survives review: what surface-to-surface volume evidence needs to show and why load counts don't hold up.

    An eroded earthen cut bank in the foreground with an excavated grading site visible on the horizon.
  11. N-08

    What counts as unclassified excavation on an earthwork bid

    What unclassified excavation covers on a bid item, how it differs from classified dirt work, and why it matters at pay app time.

    An eroded earthen cut bank exposes layers of soil in a field, with excavated mounds and access roads visible in the distance.
  12. N-07

    What is a haul distance band, and why it changes your trucking bid

    Haul distance bands set trucking cost tiers for earthwork. Here's how one-way distance, not volume, drives what your hauler bids.

    A dump truck hauling rock kicks up dust on a road at sunset, with stone rubble piled in the foreground.
  13. N-06

    Drone volume survey vs GPS machine control for verifying moved material

    A field comparison of drone volume survey and GPS machine control data for checking a dirt sub's load counts on a pay app.

    A road grader with a GPS guidance mast working on a construction site.
  14. N-05

    What is swell factor, and why it changes your truck count

    Bank yards versus loose yards, swell percentage by soil type, and why swell factor throws off your haul truck count if you ignore it.

    A dump truck driving along a dusty road past piled rock at dusk.
  15. N-04

    Bank yards vs compacted yards: why the numbers never match on your pay app

    Bank cubic yards, compacted yards, swell factor, shrinkage factor: what each term means and why they never add up to the same number.

    A dump truck hauling soil drives down a dusty dirt road, backlit by low sun.
  16. N-03

    Cross-section takeoff vs. surface-to-surface volumes: what holds up on a pay app

    How manual cross-section takeoff compares to surface-to-surface drone volume takeoff, and which one a GC can defend on a pay application.

    Large mounds of excavated soil at a construction site under an evening sky, with utility poles behind.
  17. N-02

    Load tickets don't match the survey? How to true up the pay app

    Scale tickets and the engineer's topo rarely land on the same number. Here's how to reconcile them before the pay app goes in.

    A dump truck hauling soil drives down a dusty dirt road, backlit by low sun.
  18. N-01

    What is a mass haul diagram? Reading the curve that runs your earthwork

    A mass haul diagram plots cumulative cut/fill along an alignment. How it's built, what the balance point means, and free haul vs overhaul.

    A motor grader finishes the subgrade of a new road under an overcast sky.

← Back to Earthwork Volumes