How to size a haul truck fleet from a weekly cut volume report

A dump truck parked on a dirt haul road at a quarry, with dry hills and a cloudy sky in the background.

Most haul fleet sizing starts with a number somebody half-trusts. The grading sub says 40,000 cubic yards came out of the cut this month, the super wants trucks on site Monday, and the fleet count gets worked backward from a figure nobody independently checked. That's how you end up with six trucks standing around on a day the cut only moved half what the report said, or three trucks buried under a backlog because the real number was high.

The math for sizing a fleet off a volume number is not complicated. The part worth slowing down on is which volume number you're feeding into it.

The fleet-sizing math

Once you have a cut volume you trust for the week, the rest is arithmetic:

  • Daily volume target. Take the weekly cut quantity and divide by haul days available, accounting for any days lost to weather or sequencing.
  • Truck cycle. Add up load, haul out, dump, haul back, and any queue at the cut into one cycle length. Clock a few real cycles on site rather than relying on a book number. Haul road condition and grade change this more than most schedules assume.
  • Loads per truck per day. Divide the working day (minus breaks, fueling, shift change) by the cycle time.
  • Capacity per load. Struck or heaped bed capacity for the truck class you're running, adjusted for the material.
  • Truck count. Daily volume target divided by (loads per truck per day times capacity per load), rounded up.

Run the math both ways: at the planned cut rate and at a faster rate if the excavator crew is ahead of schedule. A fleet sized for the average week gets overrun the week production spikes, and that's usually the week the super calls asking why trucks are backed up at the cut.

Why the cut volume itself needs to be right

Everything above falls apart if the input volume is wrong, and the input volume is usually a load count: trucks times rated capacity times a fudge factor for how full each load really was. That number comes from the same crew whose production it's measuring, which is not an accusation, it's just how load counts get built. A truck that's three-quarters full still gets logged as a load.

A surface-to-surface volume comparing this week's drone survey against last week's measures the cut/fill quantity moved, independent of how it was hauled or counted. Run the fleet math against that number, and cite it on the pay application line item it supports. Earthwork Volumes turns a weekly flight into exactly that cut/fill figure, built to stand behind both the haulage plan and the draw request.

Bank volume vs. loose volume

Confirm which measurement basis the report gives you before you run the bed-capacity math. Soil and rock swell when excavated, typically somewhere in the 10-30% range depending on material, so a 40,000 bank-yard cut can load out as well over 45,000 loose yards riding in truck beds. Bed capacity is a loose-yard figure. If the volume report hands you bank cubic yards and you plug that straight in without applying a swell factor for the material, the fleet comes out undersized, and it comes out undersized the same way every week until somebody catches it.

Size the fleet off a number pulled this week, not a schedule built off last month's average, and recheck it every time the cut rate changes. A fleet that matched the job in week two can be two trucks short or two trucks idle by week six if nobody's rerunning the math against current ground truth.